Increasing the quantity during the abstract or indent stage is a structured process that ensures budget and material tracking remains accurate and aligned with project requirements. This can be done at the BOQ (Bill of Quantities) level and at the Material level, depending on whether you’re working with the abstract or the indent respectively.
Abstract Stage (BOQ Qty)
To increase the quantity in an Abstract, follow these steps:
Step 1. Increase the quantity at the BOQ level / Create an additional BOQ as an alternative
Step 2. Load the BOQ in the work order.
Step 3. Increase the quantity in Abstract.
Indent Stage (Material Qty)
To increase material quantities during an Indent, the process is similar:
Step 1. Increase Material Qty at the BOQ level / Create an additional BOQ as an alternative
Step 2. Load the BOQ in the work order.
Step 3. Increase the Qty in indent.